GeoGuides

Design Approach To Two Preliminary O-Cell Tests

$1.00

Category:

Description

The original requirement for preliminary piles testing was for verifying the pile lengths that have been given in the SI report (issued by the Lab). Hence, testing the trial piles
should have been after design is completed. The agreement with the project owner was altered to optimize pile lengths.